Phase 1: Pre-Sales Discovery (أسبوع 1)
Goal: فهم البزنس + scope realistic.
Activities:
- Stakeholder interviews (CEO، CFO، COO، department heads)
- Process mapping (sales، purchase، inventory، إلخ)
- Pain points identification
- Competitive analysis (إذا كان فيه نظام حالي)
- High-level cost estimate
Deliverable: Discovery report + initial proposal
Phase 2: Detailed Scoping (أسبوع 2)
Goal: Scope مفصل قبل التوقيع.
Activities:
- Module selection + customization scope
- Integration requirements (Odoo ↔ banks، ZATCA، إلخ)
- Data migration scope (years، entities، complexity)
- Training scope (users، sessions، materials)
- Detailed timeline + resource allocation
- SOW + payment terms
Deliverable: Signed Statement of Work (SOW)
Phase 3: Project Kickoff (أسبوع 3)
Goal: Align kickoff الجميع على الـsame page.
Activities:
- Project team introduction (PM، analysts، developers)
- RACI matrix sharing
- Communication plan (weekly status، Slack channel، إلخ)
- Risk register initialization
- Tool setup (Jira، Confluence، shared drive)
Deliverable: Project charter + kickoff deck
Phase 4: Business Analysis (الأسابيع 4-5)
Goal: Document الـas-is + design الـto-be.
Activities:
- Workshops مع كل department
- Process diagrams (BPMN)
- Functional Requirements Document (FRD)
- Gap analysis (Odoo standard vs requirements)
- Customization specifications
Deliverable: FRD + customization specs + gap analysis
Phase 5: Technical Design (الأسبوع 6)
Goal: Translate الـrequirements لـtechnical design.
Activities:
- Module architecture (Python classes، models، views)
- Integration architecture (REST APIs، webhooks)
- Data model (custom fields، relationships)
- UI/UX wireframes (لو فيه custom screens)
- Security model (groups، record rules)
Deliverable: Technical Design Document (TDD)
Phase 6: Configuration + Customization (الأسابيع 7-10)
Goal: Build the system.
Activities:
- Standard Odoo configuration (chart of accounts، tax rates، journals)
- Custom module development
- Integration code (Odoo ↔ ZATCA، banks، الـ3rd-party systems)
- Reports + dashboards
- Email templates + workflows
Deliverable: Working system في staging environment
Phase 7: Data Migration (الأسابيع 9-11)
Goal: Move data clean من النظام القديم.
Activities:
- Data extraction (CSV، SQL، API exports)
- Data cleansing (deduplication، normalization)
- Data transformation (mapping للـOdoo schema)
- Test migration (multiple rounds)
- Reconciliation (trial balance، AR/AP، inventory)
Deliverable: Validated data في staging
Phase 8: User Acceptance Testing (الأسابيع 11-13)
Goal: Validate الـsystem before go-live.
Activities:
- Test scenarios writing (end-to-end workflows)
- UAT execution مع super-users
- Issue tracking + resolution
- Performance testing (لو الـvolume عالي)
- Security testing
Deliverable: Signed UAT report
Phase 9: Training (الأسبوع 13)
Goal: الـusers جاهزين للـgo-live.
Activities:
- Role-based training sessions (sales reps، AP، AR، إلخ)
- User manuals (Arabic + English)
- Quick reference cards
- Video tutorials
- Train-the-trainer (لشركات كبيرة)
Deliverable: Trained user base
Phase 10: Go-Live Preparation (الأسبوع 14)
Goal: Smooth cutover.
Activities:
- Final data migration (last 24-48 hours of legacy data)
- Reconciliation final pass
- Cut-off date communication
- Rollback plan documented
- Go-live war room scheduled
Deliverable: Go-live runbook
Phase 11: Go-Live (الأسبوع 15)
Goal: Live in production.
Activities:
- Production environment activation
- Final user access provisioning
- First transaction execution (witnessed)
- Daily standup meetings (war room)
- Hourly system health checks
Deliverable: Live system
Phase 12: Hypercare (الأسابيع 16-20)
Goal: Stabilize + transition لـsupport.
Activities:
- دعم مكثّف عن بُعد للأسابيع الأولى
- Issue tracking + rapid resolution
- Minor adjustments + tweaks
- Knowledge transfer لـSoftloomer support team
- Post-implementation review + lessons learned
Deliverable: Stable system + signed acceptance certificate